Ga naar zoeken
PALLAS New-build

About PALLAS Programme

The PALLAS Programme is an international project organisation that brings together the knowledge and expertise of professionals from more than 30 countries. United by a single goal: to safely and timely realize the PALLAS-reactor.

Read more about the design
Informatie Tentoonstellling NRG PALLAS 4
Pallas Dvdb LR DSC6360 20240608

PALLAS Programme: the merger with NRG

 

With the construction of the new PALLAS-reactor in Petten, the Netherlands takes an important step towards the future of nuclear technology. The reactor will succeed the currently opearting High Flux Reactor (HFR) and is designed for the production of medical isotopes and conducting nuclear research. 

 

In 2012, the Dutch government expressed its support for this project to maintain the Netherlands' international position in the field of medical isotopes. A year later, the PALLAS-Reactor Preparation Foundation was established to coordinate the realization of the new reactor. 

NRG PALLAS 

 

Since 2020, PALLAS and NRG have been working closely together. This collaboration led to a full merger on January 1, 2025. Since then, both organisations have formed a single entity: NRG PALLAS. Together, we are building the nuclear solutions of tomorrow, with safety and reliability as our foundation. 

Nuclear. For Life.
19Th Of May 2025 Airpicture NRG PALLAS

Meet the PALLAS Programme directors

Peter Dijk

Programme Director
Member Executive Committee NRG PALLAS

Rvc Peterdijk (5)

Arne Siewertsen

Director Finance & Control

 

Arne Siewertsen 1 Pallas 2023

Sietsche Eppinga

Construction Director

 

Sietsche Eppinga 3

Onne Wouters

Director Operational Readiness

 

Onne Wouters 1

Marjan Spronk

Manager Support & Facility Management

 

Marjan Spronk 1

Maarten Groothuis

Head of Programme Office

 

Maarten Groothuis 1 Pallas 2023

Jan van der Marel

Technical Project Director

 

Jan Van Der Marel 1 Pallas 2023
Foundation Piles 21 Oct (1)

Funding

The original aim of the PALLAS facilities was to be commercially financed, owned, and operated. In practice, this proved not feasible under conditions acceptable to the government. 

To still enable the development of the reactor, the government has provided a number of loans, so that NRG PALLAS was able to obtain permits, and have conversations with possible financiers. In a letter (dated 21 January 2022), minister Ernst Kuipers reports to the Parliament that the key question is whether the Netherlands will continue its leading role in the security of supply of medical isotopes or whether we consider a greater international dependence and uncertainties regarding future availability of medical isotopes to be acceptable and proportionate.  

The choice was the first option. In September 2022, the Ministry of Health, Welfare and Sport (VWS) reserved an initial amount of 30 million euros, followed by an annual contribution of 129 million euros. A year later, in September 2023, full financing for the construction of the reactor was confirmed. On July 26, 2024, the European Commission also gave the green light for this investment. 

The total costs of the project are estimated at 2.4 billion euros — an investment in the health of millions of patients worldwide

Energy & Health Campus

The new PALLAS-reactor is being built at the Energy & Health Campus (EHC) in Petten — a dynamic environment where more than 1,600 professionals work daily on innovative technologies and nuclear solutions for health and energy. The campus brings together knowledge, research, and production, fostering collaboration and progress.

Read more about the EHC
18 04 24 Pallas (17) Bewerkt