Curious about the progress of the PALLAS-reactor? In our media library, you'll find the latest images from the project: from construction pictures to videos showing how we are building the nuclear infrastructure of the future, step by step.

GPS Allocation
Accepteer marketingcookies om de video te bekijken

Watch our videos

Watch our video updates from the PALLAS construction site on our YouTube-page.

Vraag ChatGPT
All videos

Photos

June 2025

The works started on the construction pit of the Secondary Cooling System Building. The execution of the retention walls, which form the perimeter of the pit, commenced. These walls are executed using the Cutter Soil Mix (CSM) technique. CSM walls will enable further excavating the area to construct the building. The Secondary Cooling System Building is part of the PALLLAS-reactor secondary cooling system. 

CB2 Works Start 26 June
Beams 26 June
Beams Installation 26 June

May 2025

The Pit & Foundation phase is completed. The construction pit, a vital supporting structure that allows the construction of the PALLAS-reactor, equals in surface area to half a football field and deep enough to fit a six-storey building.

Pit And Foundation Completed
In The Pit 7 May 01
P&F Cobblestone

April 2025

A 1,5-meter-thick layer of concrete is poured across the pit in five parts. With the foundation floor of the reactor building completed, the construction pit will be delivered. 

NRG PALLAS DvB
NRG PALLAS DvB (03)
NRG PALLAS DvB

March 2025

Installation of the reinforcement bars at the bottom of the pit is being finalized. 

Rebars In The Pit 5 March
Pit Overview 19 March
Work In The Pit 19 March

February 2025

Works on the final step of the Pit & Foundation have been underway. The total of 790 tons of steel reinforcement bars (rebars) are being placed in layers at the bottom of the pit. The rebars, of which the longest ones are 14-meters long, are placed across each other in a given way to ensure the strength of a soon-to-be poured foundation floor.

Working On Rebars Installation 18 Feb
Rebars Installation In The Pit 18 Feb

January 2025

All 380 foundation piles have been filled with concrete. The concrete levelling layer has been poured around the piles to allow for the smooth start of the works on the foundation floor.  

Site Overview With Concrete Mixer
Pouring Concrete Movie Snaphot
Pile Filled With Concrete