Ga naar zoeken

December 2024

380 foundation piles are filled with concrete, integrating them as permanent components of the structure. Piles, filled with concrete and connected to the (yet to be realised) bearing slab, provide critical support for the reactor building from below. 

Piles Concrete Pour 12 Dec
Concrete Pour In Detail 12 Dec
Crane And Mixers 12 Dec

November 2024

After the top sections of the 380 foundation piles were cut off, the piles were opened and inspected. Steel reinforcement bars (rebars) have been installed in the piles to strengthen their connection with the bearing slab (foundation floor of the reactor building), which is the final step yet to be completed in the reactor building's foundation.

Pit Overview 13 November
Placing Rebars Overview
Work In The Pit 13 Nov 01

October 2024

With the fully pumped out construction pit, the works at the bottom of the pit have been underway. The top parts of 380 foundation piles remain sticking out from the concrete floor. These top parts are being cut off and in the next step, they will be opened and inspected. Placing rebars and filling piles with concrete follow.

Construction Pit 21 Oct
Foundation Piles 21 Oct
Diapghram Walls And Bottom Of The Pit

September 2024

With the foundation piles drilled and the concrete floor fully hardened, the basic foundation of the construction pit was established, which meant the water could be pumped out. A total volume of 48,000 cubic metres – equivalent to the volume of 19 Olympic swimming pools – were eventually pumped out. 

Look Into The Pit
Pit 25 Sept
Piles 25 Sept 02

August 2024

For many months, the construction pit of the PALLAS-reactor resembled a swimming pool. Water in the pit balanced ground water pressure and prevented the uplift of the bottom. With all 380 foundation piles in place and the bottom concrete floor hardened, the water started to be pumped out of the pit. The water (of which quality was tested in the lab) is being disposed to surrounding landscape according to the approval given by the authorities. Groundwater level is monitored throughout the process to ensure the water does not exceed accepted levels. 

Pit Overview 22 August
Pit Pump Out Update 22 August

July 2024

During a continuous 30-hour work, 4,000 cubic meters of concrete were poured under water at the bottom of the PALLAS-reactor construction pit to create a 1.5-meter-thick concrete layer. Prior to this, a layer of gravel had been applied in to the excavated pit to ensure a high-quality underground pour. 

Pouring Gravel 02
Pouring Gravel 01
Underwater Concrete Pour 02
Underwater Concrete Pour 01

June 2024

On 8 June, the PALLAS construction site was opened for a visit of external and internal stakeholders as part of the initiative called ‘Dag van de bouw’ (construction day). Around 450 visitors had a chance to experience the preparatory works of the PALLAS-reactor up close.

NRG PALLAS DvB
NRG PALLAS DvB (03)
NRG PALLAS DvB
NRG PALLAS  DvB (02)

May 2024

More than half of 380 foundation piles have been drilled in the ground of the reactor building. 

Pit Overview 1 May
Pile Screw Check
Pile Hoisting 02
April 2024 Energy & Health Campus luchtfoto's
EHC Luchtfoto
EHC Luchtfoto
EHC Luchtfoto
EHC Luchtfoto

April 2024

The drilling of the 380 foundation piles of the reactor building has been underway. Given that the piles are drilled under water and the quality of all work is not visible until the pit is fully pumped out, several diving inspections are conducted. A diver inspects the quality of the drilling process at the bottom of the pit.

Screw Injection Pile Screw
Pile Hoisting 01
Diver 02

March 2024

The drilling of 380 foundation piles of the reactor building to a depth of -47.0 NAP has started. To balance ground water pressure, there is still water in the pit. Therefore, the 33-meter-long piles are drilled from the pontoon, using the pile cleaning device (PCD) to accurately position the drilling pile on the bottom. 

First Pile PALLAS
Sign First Pile
Drilling Machine And The Pile

February 2024

After more than three months of digging (first by dry excavation, in the second phase by wet excavation), the pit excavation was completed. The pit is excavated and extracted sand, clay and peat have been disposed of at the sand depot. The pit is still filled with water up to the groundwater level.

Site Overview 28 Feb
Wet Excavation

January 2024

Foundation piles have been successfully tested in 5 rounds of quality tests. The tests are conducted to verify pre-determined parameters of drilling such as speed, torque, and flow speed of the grout.

Site Overview Test Piling Jolanda Approved
Test Piling (2)

Andere jaren