2023
December 2023
On 5 December 2023, PALLAS partners with FCC Construcción for the construction of the PALLAS-reactor.



November 2023 Energy & Health Campus luchtfoto's




November 2023
The pit is being dug from the ground level down to -6.0 NAP by dry excavation. Thereafter, it is wet excavated from pontoon down to -9.0 NAP, followed by pumping out the sand with water to -17.5 NAP and reaching down to a depth of 21 metres.




October 2023
Works on the anchors continue.



September 2023
The anchors, consisting of 162 bored steel tubes with 15 anchor strings, are drilled through the upper part of the diaphragm walls, and serve as a reinforcement to the diaphragm walls.



August 2023
Placement of capping beam



July 2023
Ongoing work on the pit. A ring beam will be installed after finishing the diaphragm walls.


Juli 2023 Energy & Health Campus luchtfoto's




June 2023
Trenches 1.5 meters wide have been dug into which concrete was poured to create the diaphragm walls - the first stage in the realization of the pit. Concrete is checked upon arrival at the construction site.






May 2023
First concrete pour at the construction pit of the PALLAS-reactor on 4 May 2023.

March 2023
Work area preparation