December 2023

On 5 December 2023, PALLAS partners with FCC Construcción for the construction of the PALLAS-reactor. 

Contract Signature NRG PALLAS FCC 04 (High Res)
Contract Signature NRG PALLAS FCC 05
Contract Signature NRG PALLAS FCC 01
November 2023 Energy & Health Campus luchtfoto's
Air Picture Nov 2023 (3)
Air Picture Nov 2023 (1)
Air Picture Nov 2023 (2)
Air Picture Nov 2023 (4)

November 2023

The pit is being dug from the ground level down to -6.0 NAP by dry excavation. Thereafter, it is wet excavated from pontoon down to -9.0 NAP, followed by pumping out the sand with water to -17.5 NAP and reaching down to a depth of 21 metres.

Dry Excavation 01
Digger In The Pit
Site Overview 19Nov
On The Pontoon

October 2023

Works on the anchors continue. 

Anchoring 02
Diggers 03
In The Pit

September 2023

The anchors, consisting of 162 bored steel tubes with 15 anchor strings, are drilled through the upper part of the diaphragm walls, and serve as a reinforcement to the diaphragm walls. 

Site Overview Sept 2023
Anchoring
Anchors Tensioning

August 2023

Placement of capping beam

Site View 01
Concrete Pour 01
Concrete Pour 02

July 2023

Ongoing work on the pit. A ring beam will be installed after finishing the diaphragm walls.

Grabber
Grabbers 02
Juli 2023 Energy & Health Campus luchtfoto's
2023 Campus From Above 08
2023 Campus From Above 05
2023 Campus From Above 04
2023 Campus From Above 06

June 2023

Trenches 1.5 meters wide have been dug into which concrete was poured to create the diaphragm walls - the first stage in the realization of the pit. Concrete is checked upon arrival at the construction site.

Bentoniet Storten
Bentonite Check
Diaphragm Walls 2
Site View 1
Korf
Trucks

May 2023

First concrete pour at the construction pit of the PALLAS-reactor on 4 May 2023. 

Sign

March 2023

Work area preparation 

Sign
Bouwkuip
Overview
Pipes 1